Great Blakenham: Water pumps fail at energy-from-waste incinerator causing six-week shutdown

PUBLISHED: 06:25 28 August 2014 | UPDATED: 06:25 28 August 2014

The incinerator at Great Blakenham. Photo: Barry Pullen

The incinerator at Great Blakenham. Photo: Barry Pullen

(c) copyright citizenside.com

Bosses from Suffolk’s energy-from-waste plant think they are still on schedule despite the incinerator being shut down for six weeks.

The facility based in Great Blakenham, which is intended to save £8million a year by cutting landfill charges, has not been operating since it suffered a water pump failure last month.

Although it is in its commissioning phase, where dozens of tests and checks are carried out, the incinerator had been burning waste prior to the fault.

A spokeswoman for SITA, the facility’s operator, said: “There was an issue and we have shut down for some time. I would not say it’s a major problem as we are in the commissioning phase and so we are putting the whole facility through loads of tests.

“The plant was operational but was not in full flow when we had the problem with the water pumps.

“It would be lovely if the plant was working but a plant of this size and magnitude and with this equipment was likely to have problems in the commissioning phase.”

She warned residents to expect to see pink smoke again as the boilers have to be steam cleaned before the incinerator is started up.

There were concerns raised when large clouds of the smoke were seen last month but Suffolk County Council, which has led the project, said there were no health risks.

The SITA spokeswoman added: “There is nothing to worry about; we will be doing this for at least two weeks but that could change.

“We had anticipated issues during the commissioning period; we were ahead of schedule so now we are perhaps back on schedule.”

John Field, district councillor for the area, said he was “very pleased” the plant had been ahead of schedule but stressed the importance of informing residents of progress.

The commissioning phase, which started in February, is due to end in December when the facility should be fully operational.

SITA say the incinerator will provide enough electricity to supply 30,000 homes.

The county council is to provide 170,000 tonnes of non-recyclable waste a year.

Hundreds of tonnes of waste have already been delivered to the site.

What do you think of the new incinerator? Email in at newsroom@archant.co.uk

Striking new images are being unveiled of a major development proposed for the heart of Ipswich which could see restaurants, a hotel and a tower block built opposite Cardinal Park.

Firefighters have attended a “rescue” in Ipswich.

Firefighters have been called to a blaze in a residential street in Ipswich.

The University of Essex is among more than 60 institutions set for strike action next month over pensions – however staff at the University of Suffolk are not expected to take part.

The care received by patients was assessed by an independent panel

A reality TV star was caught reading about horses while driving along a Suffolk road.

A Suffolk war hero who survived eight bomb blasts has told this newspaper a new political party launching nationwide next month aims repair the country’s public services – and give disillusioned voters a voice.

A former Ipswich man who raped and sexually assaulted a schoolgirl has been jailed for 12 years.

Temperatures in Suffolk and Essex are forecast to rival Athens in Greece tomorrow as a spell of mild weather is set to continue.

A world-renowned female harpist has denied sexually abusing a schoolboy and told a trial that he sexually assaulted her while she was in the shower.

Most read

Show Job Lists

Topic pages

Newsletter Sign Up

Sign up to receive our regular email newsletter
MyDate24 MyPhotos24