Sizewell C: Hopes of four villages A12 bypass are dashed

08:45 21 November 2012

Huge loads travelling through Farnham.

Huge loads travelling through Farnham.

Archant

HOPES that EDF will finance a major bypass for four villages on the A12 between Saxmundham and Wickham Market have been all but dashed.

Rail improvement

MAJOR rail improvements are planned to try to ensure as much of materials needed for Sizewell C do not have to arrive on Suffolk’s already-congested roads.

The freight-only Sizewell branch from Saxmundham station on the East Suffolk line is likely to be extended to the construction site.

The actual route of this extension has to be decided – the shortest route would come off the existing line in Leiston but there could be a longer extension avoiding the built-up area of the town altogether.

At the height of construction four or five trains a day could be travelling to Sizewell – sharing most of the route with passenger trains on the East Suffolk line.

Because the line is more intensively used than in the past, EDF will pay for a new passing loop to be built at Campsea Ashe, which will also need the restoration of the second platform that was demolished in the 1980s.

EDF will also look at whether it needs to improve the four level crossings on the Sizewell branch – at present they have to be opened and closed by a second crew member on the infrequent freight trains that take used fuel from Sizewell A.

If there are more trains, safety rules could require modern crossings to be installed.

As well as rail, heavy equipment for the power station is also likely to be brought to Sizewell by sea – as happened during the construction of Sizewell B.

A new jetty would be built on the coast allowing the heaviest equipment to be rolled straight off ships – however unlike the temporary jetty created for the construction of Sizewell B, elements of this could be retained permanently because it might occasionally be necessary to bring in heavy equipment.

The company’s transport strategy estimates that the station will see between 100 and 300 HGVs a day arriving at the site during peak construction.

But that will increase traffic along the A12 south of Sizewell by only 5-15% which, it says, is not enough to justify the construction of a major bypass around Farnham, Stratford St Andrew, Little Glemham and Marlesford.

It does, however, propose road improvements at Farnham – including the possible construction of a short 1km bypass removing traffic from the tight bend in the middle of the village.

However, this would do nothing to ease the traffic problems of the other villages.

Sizewell C project manager Angela Piearce said the company would still be prepared to talk to the county council about improving the road network, but felt the bypass was not necessary so far as the power station construction was concerned.

She said: “We are looking to bring in much of the heavy equipment by sea or by train rather than on the road. There will always be some equipment that has to arrive by road, but there should not be enough to justify the major bypass.”

A short by-pass for Farnham would cost several million pounds.

The company plans to create two park and ride sites for workers, allowing them to leave their cars and be driven to the site – further easing congestion around Sizewell and Leiston.

The two 1,000-space sites would be built on the A12 to the north and the south of Leiston.

One will be in the Darsham/Yoxford area, possibly beside Darsham railway station, and one near Woodbridge or Wickham Market.

The southern park and ride site could also be used as a lorry park, holding vehicles before they complete their journey to the site – another option for this is for the company to develop a new lorry park on the A14 south of Ipswich which could double as a “stack site” to hold lorries when the Port of Felixstowe is closed.

The news about the four villages will come as a body-blow to Suffolk County Council and Suffolk Coastal who issued a demand for the work to be financed by EDF just hours before the consultation document was published.

The councils released three demands:

n New local jobs and businesses and a lasting legacy of opportunity and growth.

n The highest possible environmental building standards, as the development is in an Area of Outstanding Natural Beauty.

n The construction of a “four villages bypass,” taking increased A12 traffic away from Marlesford, Little Glemham, Farnham and Stratford St Andrew.

Guy McGregor, Suffolk County Council’s cabinet member responsible for roads, transport and planning, said: “The county council recognises that the development of Sizewell C is necessary to meet the country’s energy needs and indeed supports its construction.

“However, it is important that Suffolk benefits from the development, both in terms of the local economy including improvements to local transport infrastructure and the protection of the Area of Outstanding Natural Beauty in which Sizewell C will be situated.”

Related articles

1 comment

  • What a farce. Almost as bad as the Police Commissioner elections. Nuclear is more expensive than any renewable resource. It is more polluting tham any renewable resource. Creates less jobs than any renewable respurce. It takes longer to build than any renewable resource... etc. etc. Yet all we are consulted on is whether we have an A12 bypass or not!

    Report this comment

    Pete Rowberry

    Thursday, November 22, 2012

Warning over online sextortion attempts

Sextortion’ reports to Suffolk police nearly trebled last year, according to the constabulary’s figures.

An Abellio Greater Anglia train

Frustrated rail passengers in Suffolk and Essex have signed a petition urging rail operators to reduce fairs involving bus replacement services.

Christchurch Street Ipswich

An Ipswich tenant smashed every window of an alleged drug-dealer’s car because he believed police had failed to take action.

Suffolk fire crew. Stock image.

A van on fire has closed the Station Road junction of the A137 at Tattingstone.

Footbath crossings are set to be closed on main lines in Suffolk

A total of 30 rail crossings in Suffolk could be closed in a bid to speed services on the main line to London and the cross-country route from Felixstowe to Ely and the midlands.

Holywells Park won a Civic Voice award

Holywells Park in Ipswich was one of just 11 renovation projects to scoop a national award today.

St Margarets Street, Ipswich, from Majors Corner, in the 1930s

From the Dock, now known as The Waterfront, to the streets in and around the town centre, we see many changes in Ipswich town centre.

The Suffolk Show 2015 - 
The grand parade.

The Suffolk Show has been a regular fixture on the calendars of generations of families and as this year’s event approaches, we thought we would test your knowledge of shows past and present.

An Abellio Greater Anglia train

Mainline train services running through Manningtree experienced delays of up to 25 minutes this evening.

The Deben Collective, playing a pop-up performance in Pettaugh ahead of this year's PettaFiesta festival.

The Deben Collective will be calling on Pettaugh phone-box on bank holiday Monday for a pop-up performance announcing this year’s PettaFiesta line-up.

Most read

Most commented

HOT JOBS

Show Job Lists

Topic pages

Streetlife

Newsletter Sign Up

Great British Life

Great British Life
MyDate24 MyPhotos24